In an HDB flat, replacing wall switches, adding power points or running new wiring for a smart home is electrical work. It must be carried out by an electrical worker licensed by the Energy Market Authority (EMA), supervised by the flat owner, and new wiring must be tested before use. Plugging in a smart speaker or pairing an app is not electrical work.
Key takeaways
- Any change to the fixed wiring, from swapping one switch to rewiring the flat, must be done by a licensed electrical worker (LEW), at the time of writing (October 2026).
- HDB expects the flat owner to supervise all electrical work and make sure it is installed by an EMA-licensed contractor.
- You can verify an electrician's licence on EMA's ELISE portal or from the licence card, which shows a photo, name and licence number.
- New wiring and extensions are tested through SP Services form CS/5H, and the LEW certifies the completed work.
- Every home must now have a residual current circuit breaker (RCCB), and EMA recommends testing it once a month.
What counts as electrical work in an HDB flat?
Anything that touches the fixed wiring counts as electrical work. EMA says electrical works at consumers' premises must be carried out by licensed electrical workers, and that covers rewiring, modification, alteration, repair and replacement 4.
EMA's inspectors put it simply: an LEW is needed whenever a new circuit connection is drawn, whether you are relocating a single power point or rewiring the entire home 5. Here is how common smart home tasks compare.
| Task | Electrical work? | Who does it |
|---|---|---|
| Plugging in a smart speaker or setting up an app | No | You |
| Replacing a wall switch with a smart switch or dimmer | Yes | LEW |
| Adding a lighting point, downlight or cove lighting | Yes | LEW |
| Adding a power point for a curtain motor | Yes | LEW |
| Adding or changing circuits at the distribution board | Yes | LEW |
| Installing an air-conditioner | Yes | BCA-trained installer, with an LEW for the electrical supply |
Who is allowed to do electrical work in an HDB flat?
Only an EMA-licensed electrical worker. HDB's renovation guidelines say flat owners must supervise all electrical work and ensure the installation is done by an EMA-licensed contractor, with air-conditioners installed by a BCA-trained installer 1.
A licensed electrical worker (LEW) is a person licensed by EMA to carry out electrical work. There are different classes. A Licensed Electrician may work on installations of up to 45kVA at 1,000V and below, which covers a typical flat, while technicians and engineers hold licences for larger installations 3.
Your renovation contractor for an HDB flat must also be listed in HDB's Directory of Renovation Contractors (DRC), and HDB lists the EMA-licensed electrical worker as a separate requirement for electrical installation 2. If your contractor subcontracts the wiring, the contractor must appoint an LEW of the appropriate class to take charge 3.
How do I check an electrician's licence?
Ask for the LEW's name and licence details before work starts, then check them yourself. It takes a few minutes.
- Ask your contractor which LEW will be in charge of your electrical work.
- Look up the worker on EMA's e-Licence Information Services (ELISE) portal, under the search for licensed workers 3.
- Ask to see the licence card on site. EMA says each card carries a photograph, the worker's name, identity card number and licence number 3.
- Compare fees from more than one LEW, as EMA recommends 3.
Do smart switches need an HDB permit?
Usually not, but conditions apply. HDB publishes tables of electrical works that do not need a permit; they remain subject to its guidelines and conditions, and HDB asks owners to seek approval for electrical items not listed 1.
Your flat's electrical capacity also matters. HDB says blocks completed on or after 1 January 1994, or upgraded under the Main Upgrading Programme (MUP) or Home Improvement Programme (HIP), have a 40A main switch, and a permit is not needed for air-conditioners in those flats 1. Additions must stay within the existing main switch rating 1.
Rules change, so ask your contractor to confirm what applies to your block at the time of writing (October 2026). Our guide to smart homes in resale HDB flats covers older blocks in more detail.
How is new wiring tested and certified?
New wiring is not finished when the last switch plate goes on. HDB's guidelines require SP Services form CS/5H to be submitted for testing of new wiring or extension works 1.
EMA describes the LEW's role at the end of a job: the LEW inspects and certifies the completed work and applies to SP Services for inspection, so the installation is confirmed safe before it is switched on 4. Ask for both steps to be written into your quote.
Before the electrician leaves, ask for a simple record of what was installed:
- A circuit list: which lights, sockets and smart switches are on which breaker.
- A switch plan: each panel, its keys and what each key controls.
- Product details: model names of switches, dimmers and drivers, for future repairs.
What should I check at my distribution board?
Check that it has a working residual current circuit breaker. An RCCB is a safety switch that cuts power when it detects electricity leaking to earth, for example through a faulty appliance or a person.
EMA required all residential premises to have an RCCB by 1 July 2023 7. It recommends testing it once a month by pressing its Test button, which should cut the power 6. If it does not trip, call an LEW. Adding smart switches is a good moment to have the whole board checked.
What does this mean for planning a smart home?
Treat smart home wiring as part of your electrical works, not an afterthought. Most of it happens at the same stage as the rest of the wiring, so decisions about switch positions, circuits and curtain power need to be made before the electrician arrives. See planning a smart home for your BTO.
Two points are worth raising early:
- The neutral wire: a neutral wire is the conductor that carries current back to the supply. Some smart switches need one at the switch box, so ask your LEW to check. See the no-neutral-wire question.
- Separate circuits: each lighting layer you want to dim on its own needs its own circuit. See dimmer types explained.
Our honest advice
Choose one team to plan, wire, test and hand over the smart home, so one party answers for how it behaves. Maxsen's in-house electricians handle the smart home wiring across five visits from planning to handover, working alongside your ID and contractor, so the switches you touch and the circuits behind them are designed together. See how we plan smart homes for BTO and HDB flats.
Keep the circuit list and switch plan with your flat documents. They save time on every future change.
FAQ
Can I install a smart switch myself in an HDB flat?
No. Replacing a wall switch is a change to the fixed wiring, which EMA says must be carried out by a licensed electrical worker 4. Plug-in devices that use an existing socket are different.
Is an HDB-listed renovation contractor the same as a licensed electrician?
No. HDB requires a contractor from its Directory of Renovation Contractors for renovation works, and separately requires an EMA-licensed electrical worker for electrical installation 2. Many contractors work with an LEW; ask who it is.
How do I know if my HDB flat has a 40A main switch?
HDB says blocks completed on or after 1 January 1994, or upgraded under MUP or HIP, have a 40A main switch 1. For older blocks, ask your LEW to check the board before adding loads.
Who arranges testing after new wiring is installed?
Your licensed electrical worker. HDB's guidelines require form CS/5H for testing new wiring 1, and EMA says the LEW certifies the work and applies to SP Services for inspection 4.
How often should I test my RCCB?
EMA recommends once a month: press the Test button and the switch should drop, cutting power 6. If it does not, contact a licensed electrical worker.
Sources
- "Electrical Works." Housing & Development Board renovation guidelines. hdb.gov.sg
- "Applying for Approval." Housing & Development Board. hdb.gov.sg
- "Engaging Licensed Electrical Workers." Energy Market Authority. ema.gov.sg
- "Who should I engage to assist with my electrical works (e.g. rewiring of my house)?" Energy Market Authority. ema.gov.sg
- "Five common electrical safety questions: EMA Inspectorate Department explains." Energy Market Authority, 2025. ema.gov.sg
- "Electrical Safety." Energy Market Authority. ema.gov.sg
- "Residual Current Breakers Required in All Residential Premises Built Before 1985." Energy Market Authority media release, 2023. ema.gov.sg