Your Renovation Timeline: When to Plan Lighting, Wiring and Switches

In a Singapore renovation, decide lighting, wiring and switches before ceilings and carpentry close up. Here is the order of works and HDB's rules.

By the Maxsen design team · Updated October 2026 · 7 min read

A flat mid-renovation with conduits across a bare concrete ceiling and marked light positions
Scene visualisationWiring in before the ceiling closes

In a Singapore renovation, lighting and electrical decisions must be made early, before the false ceiling, carpentry and walls close up. Fix furniture positions at the design stage, finalise every light, circuit and switch before electrical works begin, and agree cabinet lighting at the carpentry drawings. After that, moving a light means opening something up again.

Key takeaways

  • Lighting follows furniture, so fix where the bed, sofa, dining table and TV go before any wiring is drawn.
  • Every light, circuit, switch and power point should be final before the electrician starts, because coves and downlights are built into the false ceiling soon after.
  • HDB requires approved renovations to be completed within three months of the permit date in newly completed blocks and one month in existing blocks, at the time of writing (October 2026).
  • Noisy works in HDB flats are allowed only from 9 a.m. to 5 p.m. on weekdays, and not on the eve of major public holidays such as Lunar New Year, Hari Raya Puasa and Deepavali.
  • New wiring is tested before handover, so leave time for testing, scene set-up and labelling at the end.

What is the usual order of works in a Singapore renovation?

Most renovations follow the same sequence, from design to handover. The lighting decisions sit inside it, and each one has a deadline set by the stage that hides it.

StageWhat happensWhat to decide
1. DesignLayout, style, carpentry conceptsFurniture positions, scenes, switch locations
2. ApprovalsRenovation permit, or MCST approval in a condoWhich works need approval
3. Hacking and masonryWalls, floors, wet areasWall changes that move switches
4. Electrical and plumbingNew wiring and pointsEvery light, circuit, switch and power point
5. CeilingFalse ceilings and covesCove and downlight positions
6. CarpentryCabinets, wardrobes, feature wallsLights built into joinery
7. Painting and finishingPaint, fittings, switch platesFitting and switch finishes
8. Testing and handoverTesting, cleaning, set-upScenes, labels and final checks

A new BTO adds a step before design: inspect the flat and report defects. A resale flat adds an electrical check of the existing wiring. See planning a smart home for your new BTO and smart homes in resale HDB flats.

What must be decided before the electrical works?

Positions. The most expensive changes in any renovation come from late decisions about where things go, because they move wires that are already in walls and ceilings.

Before the electrician starts, fix:

  • Furniture: where the bed, sofa, dining table, TV and desk will sit.
  • Circuits: which lights share a circuit, and which need their own so they can be dimmed separately.
  • Switches: where every panel sits, its height and what each key controls.
  • Power points: for curtain motors, fans, the router and control equipment.

A circuit is a group of lights or sockets fed from one breaker at the distribution board. Our guide to planning switch panels room by room helps you check each room.

When do the ceiling and carpentry lock in the lighting?

Soon after the wiring. Coves and downlights are set into the false ceiling, and lights inside wardrobes, under kitchen cabinets and behind shelves are wired into the carpentry.

  • Before the ceiling closes: confirm cove lengths and downlight positions. They should follow the furniture plan, not a grid. See cove lighting.
  • At the carpentry drawings: mark every cabinet, wardrobe and shelf light, with its switch or sensor.
  • Before painting: choose switch plate finishes, so they arrive in time.

What HDB rules set the pace of a renovation?

HDB's renovation rules decide how long you have and when noisy work can happen, at the time of writing (October 2026).

  1. Contractor and permit: HDB requires a contractor from its Directory of Renovation Contractors (DRC) for renovation works, and the contractor submits the permit application on your behalf 1.
  2. Completion window: approved renovations must be completed within three months from the permit date in newly completed blocks, and within one month in existing blocks 2.
  3. Working hours: general renovation work may run from 9 a.m. to 6 p.m. on weekdays and Saturdays. Noisy works, such as demolishing walls, removing finishes, cutting tiles and heavy drilling, are allowed only from 9 a.m. to 5 p.m. on weekdays. No renovation is allowed on Sundays and public holidays 2.
  4. Festive eves: noisy works are also not allowed on the eve of major public holidays: New Year, Lunar New Year, Deepavali, Hari Raya Puasa and Christmas 6.
  5. Neighbours: contractors must notify households within a two-flat radius, including the floors above and below, at least five days before works start 3.
  6. New flats: in newly completed blocks, bathroom and toilet wall and floor finishes cannot be removed for three years from block completion 4.

If your renovation falls in the weeks before Chinese New Year or Hari Raya, build those quiet days into the schedule early.

How is the electrical work tested before handover?

New wiring is tested before it is used. HDB's guidelines require SP Services form CS/5H to be submitted for testing of new wiring or extensions, and the work must be done by an EMA-licensed contractor under the owner's supervision 5.

A licensed electrical worker (LEW) is a person licensed by the Energy Market Authority (EMA) to carry out electrical work. Leave time after testing for the smart home to be set up: scenes saved, keys labelled and every switch checked in every room. See HDB electrical works and smart homes.

How do condo and landed timelines differ?

The order of works is the same; the approvals differ. In a condominium, the MCST may make by-laws on how works in units are carried out and may require its approval before you start 7. Ask the management office for its renovation guidelines and permitted hours before booking contractors.

In a landed house, the scope may be larger and the approvals depend on the building works involved. See condo smart homes in Singapore for the condo route.

What should happen at handover?

A short, methodical check, room by room, before the final payment.

  1. Switch every light on and off from every switch position.
  2. Dim every dimmable light to its lowest level and watch for flicker.
  3. Run each scene and confirm it does what the switch plan says.
  4. Check that keys are labelled and the circuit list matches the distribution board.
  5. Keep the drawings, circuit list and product details with your home documents.

Our honest advice

Bring your lighting and smart home plan to the very first design meeting, and finalise every light, switch and circuit before electrical works begin. Changes on paper cost nothing; changes after the ceiling closes do.

With Maxsen, that planning happens across five visits from site planning to handover, with in-house electricians working alongside your ID and contractor, so the wiring stage and the scene set-up at the end are handled by the same team.

FAQ

When should I plan my smart home in a renovation?

At the design stage, before the electrical works begin. That is when switch positions, circuits and power points can still be changed on paper.

Can I add lights after the renovation is finished?

Some, but adding a light to a finished false ceiling or cabinet usually means opening it up, patching and repainting. It is far simpler to include it in the original lighting layout.

How long do I have to complete an HDB renovation?

At the time of writing (October 2026), HDB requires approved renovations to be completed within three months from the permit date for newly completed blocks, and within one month for existing blocks 2.

Can my contractor drill on a Saturday in an HDB flat?

No. Noisy works such as heavy drilling are allowed only from 9 a.m. to 5 p.m. on weekdays 2. Quieter work may continue on Saturdays from 9 a.m. to 6 p.m.

How much notice must neighbours be given before renovation?

Contractors must notify households within a two-flat radius, including the floors above and below, at least five days before works start 3.

Sources

  1. "Applying for Approval." Housing & Development Board. hdb.gov.sg
  2. "Important Information on Renovations." Housing & Development Board. hdb.gov.sg
  3. "Written answer by Ministry of National Development on whether HDB can make public of the renovation permits issued for authorised renovation works at HDB flats." Ministry of National Development. mnd.gov.sg
  4. "Building Works." Housing & Development Board renovation guidelines. hdb.gov.sg
  5. "Electrical Works." Housing & Development Board renovation guidelines. hdb.gov.sg
  6. "Terms and Conditions." HDB Renovation Portal, Housing & Development Board. hdb.gov.sg
  7. "Carrying Out Works in Lots." Building and Construction Authority. isomer-user-content.by.gov.sg
Talk to us

Discover a smarter way to feel at home.

Tell us about your home. We will visit, listen, and propose a home composed in light.